The Hong Kong Convention entered into force on 26 June 2025. If your ship was built before that date, you will have seen one date quoted again and again: 2030. That date is real, but for most ships it is not the date that matters. This article explains what the 2030 backstop means, why your next renewal survey is the working deadline, and how to plan the inventory work backwards from it.
The Date Everyone Quotes
IMO’s FAQ says existing ships need an International Certificate on Inventory of Hazardous Materials (ICIHM) by 26 June 2030, or earlier if the ship goes for recycling first. It is a backstop. It tells you the last possible day, not the day to aim for.
Why Your Renewal Survey Is the Real Deadline
Class societies do not issue the ICIHM on a date of your choosing. They tie it to your statutory survey cycle. DNV issues it at the first main class renewal survey after 26 June 2025 and before 2030, unless the flag administration instructs otherwise. Bureau Veritas describes the same approach: the initial survey for an existing ship is carried out at or before the renewal survey of other statutory certificates on or after 26 June 2025. ABS tells owners to request the certificate at the next renewal survey.
So the date that matters is the next renewal survey on your certificate calendar. A ship whose renewal falls soon has far less time than 2030 suggests. Some flag administrations also set their own timing, so check your flag’s circular before you plan.
Ships Already Part-Way There
- You hold an EU inventory certificate or a Statement of Compliance. You still need an ICIHM. From 9 February 2026 the new EU certificate format can be used under both the EU Regulation and the Convention.
- Your Part I has not been updated for years. ABS says some existing inventories need only a surveyor’s verification, while others need an updated Part I submitted for review. An inventory prepared under older IMO guidelines may also lack cybutryne, which was added in 2023.
- You have no inventory. Part I must be prepared and approved before the initial survey. For an existing ship that means document review plus targeted visual checks and sampling on board.
A Backward Plan From Your Survey Date
| When | What |
| 12 months before | Confirm the renewal survey date and any flag instruction on ICIHM timing. |
| 9 months | Collect drawings, equipment lists, earlier asbestos and PCB reports, coating records and supplier declarations. Check any existing Part I against the current IMO guidelines. |
| 6 months | Appoint the HazMat expert and agree the visual and sampling check plan around the trading schedule. |
| 4 to 3 months | Onboard survey, sampling and laboratory analysis. Part I report issued. |
| 2 months | Submit Part I to class for approval. |
| Survey | The surveyor verifies Part I and the ICIHM is issued. |
Marine Mechanics allows three to four months end to end for a first-time ship. Starting earlier leaves margin for laboratory and class timing.
If Part I Is Not Ready on the Day
Class needs Part I submitted and approved before it carries out the initial IHM survey. A ship that reaches its renewal survey without it risks not getting the certificate at that survey. The work is mostly document review and a planned onboard visit, so it can be fitted around the trading schedule.
Two Quick Questions
Do I need an ICIHM if I already hold an EU certificate?
When is my deadline?
Marine Mechanics is a technical engineering partner for the full vessel lifecycle. IHM is one part of that. See IHM Preparation to plan your survey, IHM Maintenance to keep Part I current afterwards, or write to mmconsultants@marinemechanics.biz.